Power Line Work on Ft. Union

Power Line Work on Ft. Union

Please be advised of upcoming day and night time power line work on Fort Union Boulevard, from March 20 to June 2.  

This work will entail the relocation of existing transmission lines to support the current road widening project taking place in the area of Highland Drive and Ft. Union Blvd. 

Location of Work: 
• S. Greenfield Way & Ft. Union Blvd. to Caden’s Cove & Ft Union Blvd. (North & South Side of Ft Union Blvd.) 
• 6850 S. & Highland Dr. to 7006 S. Highland Dr. (West Side of Highland Dr.)

Hours of Operation:
• Non-Outage Work from 8:00am – 5:00pm/ Outage Work from 8:00pm – 6 a.m. (Majority of work to be completed @ night in an effort to have minimal impact on Businesses)

UPDATE (3-28-17):
1. Wasatch Electric will continue with their line work on the 46KV and 138KV systems this week.  Work will predominantly occur at night and should not require any outages. 

2. Wasatch electric will also be cutting some of their old poles at night.  This will generate some noise and may result in the generation of sparks.  

3. Today or tomorrow they will be removing the old pole near Check City and will stand a new pole near Barbacoa. 

4. Wednesday night they will start work on the Chevron pole.  This will require southbound and eastbound lane closures. They will begin drilling at roughly 10:00 PM and plan to make the foundation concrete pour early on Thursday morning.  This activity will cause some noise and vibration.